Lots of things are changing, the process isn’t one of them.
THE PROCESS
Completed Stages
PRE-FEASIBILITY
2014 ————-> 2017
Conceptualization
FEASIBILITY
2017 ———->2020
Confirmation of business + environmental case
OPTIMIZATION
2020 —->2022
Making it safer, smarter and more sustainable
Current Stage
PERMITTING & DETAILED DESIGN + FINANCING
a safer, smarter and more sustainable Opportunity
Atlin’s Hydro Opportunity Summer 2025
What’s happening now
Clean Energy Development Plan (CEDP) documents for Atlin’s Hydro Opportunity are now available.
90% design to be complete by end of 2025
Maintain shovel ready project status
With primary permits in hand, target completion of secondary permitting to enable full construction as early as March 2026
Work to close the construction funding gap as soon as possible through additional grant funding
Future Stages
PROCUREMENT & CONSTRUCTION
2025 ——> 2029
Jobs, large economic investment, busier Atlin
COMMISSIONING
2029
Training, testing and officially turning it on.
Final stage
OPERATION & ENVIRONMENTAL MONITORING
2029 ———————————>2064+
Strengthening Atlin for many generations.
STAY ENGAGED, OFFER SUPPORT, ASK A QUESTION OR SHARE A CONCERN
Updates and new information will start flowing quickly beginning in June 2022 - sign up here to always be the first to know when updates have been released.