Lots of things are changing, the process isn’t one of them.

THE PROCESS

Completed Stages

PRE-FEASIBILITY

2014 ————-> 2017

Conceptualization

FEASIBILITY

2017 ———->2020

Confirmation of business + environmental case

OPTIMIZATION

2020 —->2022

Making it safer, smarter and more sustainable

Current Stage

PERMITTING & DETAILED DESIGN + FINANCING

a safer, smarter and more sustainable Opportunity

Atlin’s Hydro Opportunity Summer 2025

What’s happening now

Clean Energy Development Plan (CEDP) documents for Atlin’s Hydro Opportunity are now available.

  • 90% design to be complete by end of 2025

  • Maintain shovel ready project status

  • With primary permits in hand, target completion of secondary permitting to enable full construction as early as March 2026

  • Work to close the construction funding gap as soon as possible through additional grant funding

Future Stages

PROCUREMENT & CONSTRUCTION

2025 ——> 2029

Jobs, large economic investment, busier Atlin

COMMISSIONING

2029

Training, testing and officially turning it on.

Final stage

OPERATION & ENVIRONMENTAL MONITORING

2029 ———————————>2064+

Strengthening Atlin for many generations.

STAY ENGAGED, OFFER SUPPORT, ASK A QUESTION OR SHARE A CONCERN

Updates and new information will start flowing quickly beginning in June 2022 - sign up here to always be the first to know when updates have been released.